VisionCore
Home Search Support Forum Knowledge Base Print

Calculate Through options

Open Year Amount

When you select the Open Year Amount as the Calculate Through, you will be able to enter an Amount in the Type/Value field. You may Increase or Decrease the budget by the Amount you entered in the Type/Value field using the Increase or Decrease checkbox.

 

For example, the balance of the selected account in 2006 Period 1 (January) is $1,000.00 and you want to increase it by $200 for 2007. Just type 200.00 in the Type/Value field, select the Increase check box then click the Calculate button.

 

openyr1

 

You would notice that your budget in 2007 Period 1 (January) is now $1,200.00.

 

openyr2

 

Open Year Percent

When you selected the Open Year Percent as the Calculate Through, you will be able to enter a Percent in the Type/Value field. You may Increase or Decrease the budget by the Percent you entered in the Type/Value field.

 

For example, the balance of the selected account in 2006 Period 1 (January) is $1,000.00 and you want to increase it by 10%, (10% of 1,000.00 is equal to 100) for 2007.  Just type 10% in the Type/Value field, select the Increase check box then click the Calculate button.

 

yrpercent1

 

You would notice that your budget in 2007 Period 1 (January) is now $1,100.00.

 

yrpercent2

 

Other Budget Percent

When you selected the Other Budget Percent as the Calculate Through, the Source Budget field will be enabled and you will be able to enter a Percent in the Type/Value field. You may Increase or Decrease the budget by the Percent you entered in the Type/Value field.

 

For example, the balance of the selected account in 2006 Period 1 (January) is $1,000.00 and you want to increase it by 10%, (10% of 1,000.00 is equal to 100) for 2007.  Just type 10% in the Type/Value field, select the Increase check box then click the Calculate button.

 

otherbud1

 

You would notice that your budget in 2007 Period 1 (January) is now $1,100.00.

otherbud2

 

Set Amount

This method sets all the budgets of the Account to a specified amount in the Type/Value Field.

 

For example, You want to set all the budgets for 2007 to $2,500.00.  Just type 2,500.00 in Type/Value field then click the Calculate button

 

setamt1

 

You would notice that your budget for all the periods in 2007 is now $2,500.00.

 

setamt2

 

Yearly Amount

This method sets the value of each period to the given value in the Type/Value field divided by the number of Periods of the given Account.

 

For example, You want to set the yearly budget for 2007 to $12,000.00.  Just type 12,000.00 in Type/Value field then click the Calculate button

 

yearly1

 

You would notice that each period has a budget of $1,000.00 ($12000/12periods).

 

yearly2